This paper investigates a particular integrated lotsizing and scheduling problem in a multi-level multi-product, multi-machine and flexible routes environment that is called flexible job shop problem (FJSP). The considered problem involves making simultaneous decision in sequencing operations, sizing lots and assigning machines to operations in order to optimize a multi-objective function including minimizing sum of the system costs, total machines workload and makespan, while a given demand is fulfilled without backlogging. Due to the complexity of the problem, a hybrid meta-heuristic based on a combination of Genetic algorithm and particle swarm optimization algorithm is developed to solve it. Additionally, the Taguchi method is employed to calibrate the influential parameters of the meta-heuristic and boost its capabilities. Finally, the performance of the proposed algorithm is compared with some well-known multi-objective algorithms such as NSGAII, SPEA2 and VEGA. Regarding to the computational results, the hybrid algorithm surpasses the other algorithms in the closeness of solutions to pareto optimal front and diversity criteria.
Accepté le :
DOI : 10.1051/ro/2015049
Mots-clés : Lot-sizing, scheduling, flexible job shop, genetic algorithm, particle swarm optimization algorithm, TOPSIS
@article{RO_2016__50_3_587_0, author = {Rohaninejad, Mohammad and Sahraeian, Rashed and Nouri, Behdin Vahedi}, title = {Multi-objective optimization of integrated lot-sizing and scheduling problem in flexible job shops}, journal = {RAIRO - Operations Research - Recherche Op\'erationnelle}, pages = {587--609}, publisher = {EDP-Sciences}, volume = {50}, number = {3}, year = {2016}, doi = {10.1051/ro/2015049}, mrnumber = {3538842}, zbl = {1351.90100}, language = {en}, url = {http://archive.numdam.org/articles/10.1051/ro/2015049/} }
TY - JOUR AU - Rohaninejad, Mohammad AU - Sahraeian, Rashed AU - Nouri, Behdin Vahedi TI - Multi-objective optimization of integrated lot-sizing and scheduling problem in flexible job shops JO - RAIRO - Operations Research - Recherche Opérationnelle PY - 2016 SP - 587 EP - 609 VL - 50 IS - 3 PB - EDP-Sciences UR - http://archive.numdam.org/articles/10.1051/ro/2015049/ DO - 10.1051/ro/2015049 LA - en ID - RO_2016__50_3_587_0 ER -
%0 Journal Article %A Rohaninejad, Mohammad %A Sahraeian, Rashed %A Nouri, Behdin Vahedi %T Multi-objective optimization of integrated lot-sizing and scheduling problem in flexible job shops %J RAIRO - Operations Research - Recherche Opérationnelle %D 2016 %P 587-609 %V 50 %N 3 %I EDP-Sciences %U http://archive.numdam.org/articles/10.1051/ro/2015049/ %R 10.1051/ro/2015049 %G en %F RO_2016__50_3_587_0
Rohaninejad, Mohammad; Sahraeian, Rashed; Nouri, Behdin Vahedi. Multi-objective optimization of integrated lot-sizing and scheduling problem in flexible job shops. RAIRO - Operations Research - Recherche Opérationnelle, Tome 50 (2016) no. 3, pp. 587-609. doi : 10.1051/ro/2015049. http://archive.numdam.org/articles/10.1051/ro/2015049/
MIP-based heuristics for multi-item capacitated lot-sizing problem with setup times and shortage costs. RAIRO: OR 41 (2007) 171–192. | DOI | Numdam | MR | Zbl
and ,Two metaheuristic methods for the common cycle economic lot sizing and scheduling in flexible flow shops with limited intermediate buffers: The finite horizon case. Appl. Math. Comput. 183 (2006) 634–645. | DOI | MR | Zbl
, and ,Minimization of weighted earliness and tardiness for no-wait sequence-dependent setup times flowshop scheduling problem. Comput. Ind. Eng. 64 (2013) 902–916. | DOI
and ,Rolling-horizon and fix-and-relax heuristics for the parallel machine lot-sizing and scheduling problem with sequence-dependent set-up costs. Comput. Oper. Res. 35 (2008) 3644–3656. | DOI | Zbl
, , and ,K. Deb, Multi-objective Optimization Using Evolutionary Algorithms. Vol. 2012. John Wiley & Sons, Chichester (2001). | MR | Zbl
A fast and elitist multi-objective genetic algorithm: NSGA-II. IEEE Trans. Evol. Comput. 6 (2002) 182–197. | DOI
, , and ,Lagrangean Heuristic for a Multi–Plant Lot–Sizing Problem with Transfer and Storage Capacities. RAIRO: OR 47 (2013) 429–443. | DOI | Numdam | MR | Zbl
, and ,A particle swarm optimization for solving joint pricing and lot-sizing problem with fluctuating demand and trade credit financing. Comput. Ind. Eng. 60 (2011) 127–137. | DOI
and ,Simultaneous lot sizing and scheduling for multi-product multi-level production. Int. J. Prod. Econ. 104 (2006) 308–316. | DOI
and ,Solving the integrated lot-sizing and job-shop scheduling problem. Int. J. Prod. Res. 52 (2014) 5236–5254. | DOI
, and ,Lot sizing and scheduling with sequence-dependent setup costs and times and efficient rescheduling opportunities. Int. J. Prod. Econ. 66 (2000) 159–169. | DOI
and ,Solving uncapacitated multilevel lot-sizing problems using a particle swarm optimization with flexible inertial weight. Comput. Math. Appl. 57 (2009) 1748–1755. | DOI | MR | Zbl
, , and ,C.L. Hwang and K. Yoon, Multiple Attributes Decision Making. Lect. Notes Econ. Math. Syst. Springer, Heidelberg (1981). | MR | Zbl
Two hybrid meta-heuristics for the finite horizon ELSP in flexible flow lines with unrelated parallel machines. Appl. Math. Comput. 186 (2007) 230–245. | DOI | MR | Zbl
, , and ,Proportional lot-sizing and scheduling problem with identical parallel machines. Int. J. Prod. Res. 49 (2011) 2605–2623. | DOI
,The capacitated lot sizing problem: a review of models and algorithms. Omega 31 (2003) 365–378. | DOI
, and ,Multi-period lot sizing and job shop scheduling with compressible process times for multilevel product structures. Int. J. Prod. Res. 51 (2013) 6229–6246. | DOI
, , and ,The deterministic dynamic product cycling problem. Oper. Res. 33 (1985) 326–345. | DOI | Zbl
and ,A discrete particle swarm optimization algorithm for scheduling parallel machines. Comput. Ind. Eng. 56 (2009) 216–223. | DOI
and ,An efficient MIP model for the capacitated lot-sizing and scheduling problem with sequence-dependent setups. Int. J. Prod. Econ. 118 (2009) 282–291. | DOI
, and ,Multilevel capacitated lot-sizing complexity and LP-based heuristics. Eur. J. Oper. Res. 53 (1991) 131–148. | DOI | Zbl
, and ,Simultaneous Lot Sizing and Scheduling in a Flexible Flow Line. J. Ind. Syst. Eng. 5 (2011) 107–119.
, and ,Capacitated lot sizing with linked lots for general product structures in job shops. Comput. Ind. Eng. 58 (2010) 151–164. | DOI
and ,Fuzzy job shop scheduling with lot-sizing. Ann. Oper. Res. 159 (2008) 275–292. | DOI | MR | Zbl
, , , and ,Hybrid simulated annealing and MIP-based heuristics for stochastic lot-sizing and scheduling problem in capacitated multi-stage production system. Appl. Math. Model. 37 (2013) 5134–5147. | DOI | MR | Zbl
and ,MIP formulation and heuristics for multi-stage capacitated lot-sizing and scheduling problem with availability constraints. J. Manufact. Syst. 32 (2013) 392–401. | DOI
, and ,Integrated lot-sizing and scheduling with overlapping for multi-level capacitated production system. Int. J. Comput. Integr. Manufact. 26 (2013) 681–695. | DOI
, and ,M. Rohaninejad, A. Kheirkhah, P. Fattahi and B. Vahedi-Nouri, A hybrid multi-objective genetic algorithm based on the ELECTRE method for a capacitated flexible job shop scheduling problem. Int. J. Adv. Manufact. Technol. (2014) 1–16.
Two hybrid tabu search–firefly algorithms for the capacitated job shop scheduling problem with sequence-dependent setup cost. Int. J. Comput. Integr. Manufact. 28 (2015) 470–487. | DOI
, , and ,J.D. Schaffer, Multiple objective optimization with vector evaluated genetic algorithms. In Proc. of the 1st international Conference on Genetic Algorithms. L. Erlbaum Associates Inc. (1985) 93–100. | Zbl
Combining the principles of variable neighborhood decomposition search and the fix & optimize heuristic to solve multi-level lot-sizing and scheduling problems. Comput. Oper. Res. 40 (2013) 303–317. | DOI | MR | Zbl
, and ,A genetic algorithm for integrating lot-sizing and sequencing in scheduling a capacitated flow line. Comput. Ind. Eng. 30 (1996) 969–981. | DOI
,Multi-level single machine lot-sizing and scheduling with zero lead times. Eur. J. Oper. Res., 209 (2011) 241–252. | DOI | MR | Zbl
,Equivalence classes of problem instances for a continuous-time lot sizing and scheduling problem. Eur. J. Oper. Res. 199 (2009) 139–149. | DOI | MR | Zbl
and ,C.J. Wu and M.S. Hamada, Experiments: Planning, Analysis, and Optimization. Wiley (2011). | Zbl
An improved particle swarm optimisation with a linearly decreasing disturbance term for flow shop scheduling with limited buffers. Int. J. Comput. Integr. Manufact. 27 (2014) 488–499. | DOI
, , and ,E. Zitzler, M. Laumanns and L. Theile, SPEA2: Improving the strength Pareto evolutionary algorithm. Technical Report (2001).
Cité par Sources :