Economic lot-size problem for a cleaner manufacturing system with warm-up period
RAIRO - Operations Research - Recherche Opérationnelle, Tome 54 (2020) no. 5, pp. 1495-1514.

There are instances that production machines require a warm-up period to reach their anticipated productivity. This study extends an economic manufacturing quantity (EMQ) problem by considering warm-up issue in the model. Warming up the machine decreases production loss, emission, and machine depreciation. Therefore, this study helps industry to enhance the profitability and also to reduce the environmental impact by decreasing waste generation and improving machine efficiency. In this study, we divide our system into three subsystems based on the relationships between production and consumption. Then we provide a mathematical model for each subsystem (three in total). The first two models are single-item EMQ inventory problems and the third one is a multi-item single-machine EMQ problem. In the third model, a machine/facility manufactures some items under a limited manufacturing volume. The purpose of these proposed models is to find the optimum cycle length to minimize the total system cost that consists of manufacturing, inventory and setup costs. Finally, we propose exact solution procedures after proving the convexity of these mathematical models.

Reçu le :
Accepté le :
Première publication :
Publié le :
DOI : 10.1051/ro/2019056
Classification : 90C30, 90B05
Mots-clés : Economic manufacturing quantity (EMQ), single machine production, warm-up period, non-linear programming (NLP), exact solution
@article{RO_2020__54_5_1495_0,
     author = {Nobil, Amir Hossein and Kazemi, Abolfazl and Taleizadeh, Ata Allah},
     title = {Economic lot-size problem for a cleaner manufacturing system with warm-up period},
     journal = {RAIRO - Operations Research - Recherche Op\'erationnelle},
     pages = {1495--1514},
     publisher = {EDP-Sciences},
     volume = {54},
     number = {5},
     year = {2020},
     doi = {10.1051/ro/2019056},
     mrnumber = {4126317},
     language = {en},
     url = {http://archive.numdam.org/articles/10.1051/ro/2019056/}
}
TY  - JOUR
AU  - Nobil, Amir Hossein
AU  - Kazemi, Abolfazl
AU  - Taleizadeh, Ata Allah
TI  - Economic lot-size problem for a cleaner manufacturing system with warm-up period
JO  - RAIRO - Operations Research - Recherche Opérationnelle
PY  - 2020
SP  - 1495
EP  - 1514
VL  - 54
IS  - 5
PB  - EDP-Sciences
UR  - http://archive.numdam.org/articles/10.1051/ro/2019056/
DO  - 10.1051/ro/2019056
LA  - en
ID  - RO_2020__54_5_1495_0
ER  - 
%0 Journal Article
%A Nobil, Amir Hossein
%A Kazemi, Abolfazl
%A Taleizadeh, Ata Allah
%T Economic lot-size problem for a cleaner manufacturing system with warm-up period
%J RAIRO - Operations Research - Recherche Opérationnelle
%D 2020
%P 1495-1514
%V 54
%N 5
%I EDP-Sciences
%U http://archive.numdam.org/articles/10.1051/ro/2019056/
%R 10.1051/ro/2019056
%G en
%F RO_2020__54_5_1495_0
Nobil, Amir Hossein; Kazemi, Abolfazl; Taleizadeh, Ata Allah. Economic lot-size problem for a cleaner manufacturing system with warm-up period. RAIRO - Operations Research - Recherche Opérationnelle, Tome 54 (2020) no. 5, pp. 1495-1514. doi : 10.1051/ro/2019056. http://archive.numdam.org/articles/10.1051/ro/2019056/

[1] M. Ben-Daya and M. Hariga, Economic lot scheduling problem with imperfect production processes. J. Oper. Res. Soc. 51 (2000) 875–881. | DOI | Zbl

[2] Y.P. Chiu, Determining the optimal lot size for the finite production model with random defective rate, the rework process, and backlogging. Eng. Optimiz. 35 (2003) 427–437. | DOI

[3] S.W. Chiu, S.L. Wang and Y.S.P. Chiu, Determining the optimal run time for EPQ model with scrap, rework, and stochastic breakdowns. Eur. J. Oper. Res. 180 (2007) 664–676. | DOI | Zbl

[4] M. De, B. Das and M. Maiti, Quality and pricing decisions for substitutable items under imperfect production process over a random planning horizon. Hacet. J. Math. Stat. 47 (2018) 175–201. | MR

[5] S. Eilon, Scheduling for batch production. J. Inst. Prod. Eng. 36 (1957) 549–570. | DOI

[6] S.E. Elmaghraby, The economic lot scheduling problem (ELSP): review and extensions. Manage. Sci. 24 (1978) 587–598. | DOI | Zbl

[7] B.C. Giri, I. Moon and W.Y. Yun, Scheduling economic lot sizes in deteriorating production systems. Nav. Res. Log. 50 (2003) 650–661. | DOI | MR | Zbl

[8] R. Haji and B. Haji, Optimal batch production for a single machine system with accumulated defectives and random rate of rework. J. Ind. Syst. Eng. 3 (2010) 243–256.

[9] R. Haji, A. Haji, M. Sajadifar and S. Zolfaghari, Lot sizing with non-zero setup times for rework. J. Syst. Sci. Syst. Eng. 17 (2008) 230–240. | DOI

[10] K. Inderfurth, G. Lindner and N.P. Rachaniotis, Lot sizing in a production system with rework and product deterioration. Int. J. Prod. Res. 43 (2005) 1355–1374. | DOI | Zbl

[11] K.N.F. Leung, Optimal production lot sizing with backlogging, random defective rate, and rework derived without derivatives. Proc. Inst. Mech. Eng. Part B: J. Eng. Manuf. 223 (2009) 1081–1084. | DOI

[12] A.K. Manna, B. Das, J.K. Dey and S.K. Mondal, Two layers green supply chain imperfect production inventory model under bi-level credit period. Tékhne 15 (2017) 124–142. | DOI

[13] A.K. Manna, J.K. Dey and S.K. Mondal, Imperfect production inventory model with production rate dependent defective rate and advertisement dependent demand. Comput. Ind. Eng. 104 (2017) 9–22. | DOI

[14] A.K. Manna, J.K. Dey and S.K. Mondal, Two layers supply chain in an imperfect production inventory model with two storage facilities under reliability consideration. J. Ind. Prod. Eng. 35 (2018) 57–73.

[15] A.K. Manna, B. Das and S. Tiwari, Impact of carbon emission on imperfect production inventory system with advance payment base free transportation. RAIRO-Oper. Res. (2019). DOI: . | DOI | Numdam | MR

[16] I. Moon, B.C. Giri and K. Choi, Economic lot scheduling problem with imperfect production processes and setup times. J. Oper. Res. Soc. 53 (2002) 620–629. | DOI | Zbl

[17] A.H. Nobil, E. Nobil and L.E. Cárdenas-Barrón, Some observations to: lot sizing with non-zero setup times for rework. Int. J. Appl. Comput. Math. 3 (2017) 1511–1517. | DOI | MR

[18] A.H. Nobil, A.H.A. Sedigh and L.E. Cárdenas-Barrón, A multiproduct single machine economic production quantity (EPQ) inventory model with discrete delivery order, joint production policy and budget constraints. Ann. Oper. Res. (2017) 1–37. | MR | Zbl

[19] A.H. Nobil, A.H. Afshar Sedigh, S. Tiwari and H.M. Wee, An imperfect multi-item single machine production system with shortage, rework, and scrapped considering inspection, dissimilar deficiency levels, and non-zero setup times. Sci. Iran. 26 (2019) 557–570.

[20] A.H. Nobil, S. Tiwari and F. Tajik, Economic production quantity model considering warm-up period in a cleaner production environment. Int. J. Prod. Res. 57 (2019) 4547–4560. | DOI

[21] M. Parveen and T.V.V.L.N. Rao, Optimal cycle length and number of inspections in imperfect production processes with investment on setup cost reduction and quality improvement. Int. J. Manuf. Res. 4 (2009) 17–36. | DOI

[22] S.H.R. Pasandideh, S.T.A. Niaki, A.H. Nobil and L.E. Cárdenas-Barrón, A multiproduct single machine economic production quantity model for an imperfect production system under warehouse construction cost. Int. J. Prod. Econ. 169 (2015) 203–214. | DOI

[23] J. Quenniche and F. Boctor, Sequencing, lot sizing and scheduling of several products in job shops: the common cycle approach. Int. J. Prod. Res. 36 (1998) 1125–1140. | DOI | Zbl

[24] J. Rogers, A computational approach to the economic lot scheduling problem. Manage. Sci. 4 (1958) 264–291. | DOI

[25] S. Shafiee-Gol, M.M. Nasiri and A.A. Taleizadeh, Pricing and production decisions in multi-product single machine manufacturing system with discrete delivery and rework. Opsearch 53 (2016) 873–888. | DOI | MR

[26] E.W. Taft, The most economical production lot. Iron Age 101 (1918) 1410–1412.

[27] A.A. Taleizadeh and H.M. Wee, Manufacturing system with immediate rework and partial backordering. Int. J. Adv. Oper. Manage. 7 (2015) 41–62.

Cité par Sources :